Project Status
UPDATE: The Bond 2019 project at Foster Elementary , and renovations are getting started this summer.
New playgrounds for Foster were in phase three and are now open.
Project Scope
- Heating & A/C, Electrical, Plumbing Improvements
- Interior Renovations (Paint, flooring, ceilings, lighting, etc.)
- ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
- Restroom renovations
- Site Improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
- Roof renovations
- Paving Improvements
This list is not comprehensive and is subject to change.
- Full-day Pre-K Renovations Specific to Campus Needs
- Gymnasium Replacement
- Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
- Instruments
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades and Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 2
CONSTRUCTION
Start: Spring 2024Â Â Â Finish: Fall 2025
ARCHITECT
Perkins & Will
CONSTRUCTION MANAGER
Construction Zone
PHASE
Phase 3
CONSTRUCTION DATES
Start: Fall 2023Â Â Finish: Fall 2023
·¡±·³Ò±õ±··¡·¡¸éÌý
Glenn Engineering
GENERAL CONTRACTOR
J Squared (concrete/earthwork)
Lea Park & Play (playground equipment and install)