Duff Links
Duff Playgrounds
Duff Construction
Project Status
UPDATE: The Bond 2019 project at Duff Elementary is in phase two of the five-year bond program.
Construction started last summer. The old metal gym was demolished last July to make way for a new gym. Construction is getting close to being done and the new gym should open in November.
There was a lot of work done inside the existing building, too, during the summer, from restroom renovations to new ceilings in all the corridors and the cafeteria. Plus, a new sprinkler system was installed throughout the school and some new light fixtures were installed in some classrooms.
The new library is coming along, too, and will open by the end of August. The old library was demolished along with an adjacent classroom which is being absorbed into what is a bigger, better library.
Read more about all of the projects planned for Duff. demolition photos.
The new playgrounds for Duff were in phase one and are complete. .
Project Scope
- Kitchen Renovations
- Heating & A/C, Electrical, Plumbing Improvements
- Interior Renovations (Paint, flooring, ceilings, lighting, etc.)
- ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
- Restroom renovations
- Site Improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
- Paving Improvements
- Exterior Window Renovations
This list is not comprehensive and is subject to change.
- Gymnasium Replacement
- Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
- Instruments
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades and Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 2
CONSTRUCTION
Start: Summer 2023Â Â Â Finish: Fall 2024
ARCHITECT
WRA Architects
CONSTRUCTION MANAGER
MDI General Contractors
PHASE
Phase 1
CONSTRUCTION
Start: Spring 2021Â Â Â Finish: Summer 2021
·¡±·³Ò±õ±··¡·¡¸éÌý
Glenn Engineering
CONSTRUCTION
Reeder Concrete Inc. (concrete flatwork)Â
Miracle Recreation Equipment (playground equipment and install)