Hale Links
Construction Photos
Hale Playgrounds
Project Status
UPDATE: The Bond 2019 project at Hale Elementary is substantially complete.
Inside highlights included repainting metal doors, replacing the gym floor, refinishing the custodial closets, replacing the flooring in the teacher’s lounge, replacing the ceiling in the kitchen and installing a new HVAC controls system.
Outside, project highlights included replacing fallen concrete sidewalks and patio, installing a swale at the front for better drainage, regrading and sodding around the building and replacing the marquee with a new digital one.
New playgrounds for Hale are also now open.
Project Scope
- Heating & A/C and Electrical Improvements
- Interior Renovations (Flooring, etc.)
- ADA Accessibility Improvements (Door hardware, ramps, restrooms, etc.)
- Site Improvements (Lighting, landscaping, drainage, irrigation, signage, etc.)
- Paving Improvements
This list is not comprehensive and is subject to change.
- Full-day Pre-K Renovations Specific to Campus Needs
- Playground Replacements and Renovations (Surface, equipment, canopy, ADA accessible)
- Instruments
- Gym Floor Replacements
This list is not comprehensive and is subject to change.
- Expanded Security Camera Coverage and Upgraded Camera Software
- Safety & Security Enhancements (Exterior and interior key system upgrades, district communication system upgrades, lighting, fencing, etc.)
- Device Upgrades and Expanded Access
This list is not comprehensive and is subject to change.
PHASE
Phase 2
CONSTRUCTION
Start: Summer 2023Â Â Â Finish: Summer 2024
ARCHITECT
JR2 Architects
CONSTRUCTION MANAGER
Falkenberg Construction
PHASE
Phase 3
CONSTRUCTION
Start: Fall 2023Â Â Â Finish: Fall 2023
·¡±·³Ò±õ±··¡·¡¸éÌý
Glenn Engineering
CONSTRUCTION
J Squared (concrete/earthwork)
Lea Park & Play (playground equipment and install)