TRACK CONSTRUCTION
Phase: Three
Architect: Stantec
Construction Manager: Hellas Construction
Start Construction:Â Spring 2018
Finish: Fall 2018*
*Dates are projections and subject to change.
LIFECYCLE & DEFICIENCY
Phase: Five
Architect: LBL Architects
Construction Manager: Big Sky Construction
Start Construction:Â Spring 2019*
Finish: Fall 2019*
*Dates are projections and subject to change.
Project Status: Substantially Complete
Young's lifecycle and deficiency scope wrapped up over the winter break when a switchgear was replaced. Other scope included redoing the north parking lot, installing new fiber optic cable, and repurposing two existing locker banks into a black box theater and multipurpose classroom. A couple roof-top HVAC units were also replaced.
Construction of Young's new four-lane regulation track is also complete.
Project Scope
- Upgrade technology connectivity
- Improve existing site accessibility
- Add additional card access controls
- Replace parking
- Repair/replace and upgrade heating and A/C, electrical, electrical equipment, interior finishes, plumbing, landscaping and site lighting
- Upgrade security cameras (to be done by AISD security department)
- Add new 4-lane track (separate)
This report includes highlights of projects. The list is not comprehensive and is subject to modification.