TRACK CONSTRUCTION

Phase: Three

Architect: Stantec

Construction Manager: Hellas Construction

Start Construction: Spring 2018
Finish: Fall 2018*
*Dates are projections and subject to change.



LIFECYCLE & DEFICIENCY
Phase:
Five

Architect: LBL Architects

Construction Manager: Big Sky Construction

Start Construction: Spring 2019*
Finish: Fall 2019*
*Dates are projections and subject to change.


 

Project Status: Substantially Complete

Young's lifecycle and deficiency scope wrapped up over the winter break when a switchgear was replaced. Other scope included redoing the north parking lot, installing new fiber optic cable, and repurposing two existing locker banks into a black box theater and multipurpose classroom. A couple roof-top HVAC units were also replaced.

Construction of Young's new four-lane regulation track is also complete.


Project Scope

  • Upgrade technology connectivity
  • Improve existing site accessibility
  • Add additional card access controls
  • Replace parking
  • Repair/replace and upgrade heating and A/C, electrical, electrical equipment, interior finishes, plumbing, landscaping and site lighting
  • Upgrade security cameras (to be done by AISD security department)
  • Add new 4-lane track (separate)

This report includes highlights of projects. The list is not comprehensive and is subject to modification.