Carter Resources


Information and Links:

础诲诲谤别蝉蝉:听



FIELD RENOVATIONS
Phase: Three

Architect: Stantec

Construction Manager: Hellas Construction

Start Construction:聽Spring 2018
Finish: Fall 2018*
*Dates are projections and subject to聽change.



LIFECYCLE/DEFICIENCY WORK

Phase:
Four

Architect: VLK Architects

Construction Manager: Reeder General Contractors Inc.

Start Construction: Fall 2018*
Finish: Summer 2019*
*Dates are projections and subject to聽change.


Project Status: Substantially Complete聽

Athletic field renovations started in March and are now substantially complete. Sod for the field was installed at the end of November. The grass is now dormant for winter and will need time to take, so the field should be ready for use in the spring. The project also included re-doing some parking and installing a new concrete athletic court.

The lifecycle and deficiency scope is substantially complete and included major HVAC renovations, new water fountains and new paving and parking at the front entrance.


Project Scope

  • Upgrade technology connectivity
  • Identify existing site accessibility
  • Add additional card access controls
  • Replace and add parking
  • Repair/replace and upgrade heating and A/C, electrical, interior finishes, plumbing, exterior, landscaping and site lighting
  • Replace roof
  • Replace outside blacktop area
  • Improve site drainage
  • Renovate athletic fields

This report includes highlights of projects. The list is not comprehensive and is subject to modification.